Costs and revenues — 3 chargers, 5 years from project start
Construction and operation are separated below. Traditional charging uses electricity and earns revenue for three years; battery-integrated charging does so for four years and nine months. Both are measured from the same project-start date.
| Time, cost or revenue | Traditional: 3 chargers | Battery-integrated: 3 chargers | Calculation basis |
|---|---|---|---|
| Project period | 60 months | 60 months | Same five years from project start. |
| Installation period | 24 months | 3 months | No charging revenue or operating electricity during construction. |
| Revenue-producing / electricity-use period | 36 months (3 years) | 57 months (4 years, 9 months) | A three-month build leaves 57—not 60—operating months inside five project years. |
| Charger purchases | $180,000 | $600,000 | 3 chargers × $60,000 or $200,000. |
| Electrical upgrades & installation | $480,000 | $45,750 | Document’s per-charger allowances × 3. Assumes each installation needs its own listed scope. Shared infrastructure could change these estimates. |
| Total installed capital | $660,000 | $645,750 | 3 × $220,000 versus 3 × $215,250. |
| Electricity cost during actual operating months | $905,086.45 | $922,777.23 | Traditional: 36 operating months only. Battery-integrated: 57. Uses estimated SDG&E EV-HP annual-average bills and 1.5% escalation at project-year anniversaries. |
| Total priced cash costs | $1,565,086.45 | $1,568,527.23 | Installed capital + electricity within the common 60 months. |
| Daily delivered energy per charger | 800 kWh | 800 kWh | 200 kW × 4 full-output-equivalent hours per day. Actual battery dispatch must support this workload. |
| Charging revenue per month — 3 chargers | $43,200 | $43,200 | 800 kWh × 30 days × $0.60/kWh × 3 chargers. |
| Charging revenue over actual operating months | $1,555,200.00 | $2,462,400.00 | Monthly charging revenue × 36 or 57 months. |
| LCFS revenue per month — 3 chargers | $2,592 | $2,592 | Word document assumption: $864 per charger per month × 3. Credit ownership, eligible volume and value require confirmation. |
| LCFS revenue over actual operating months | $93,312.00 | $147,744.00 | Monthly LCFS revenue × 36 or 57 months. |
| Advertising revenue over actual operating months | $43,200.00 | $68,400.00 | Word document assumption: $400 per charger per month × 3 × operating months. Assumes a paid advertising arrangement for each unit. |
| Total gross revenue | $1,691,712.00 | $2,678,544.00 | Charging + LCFS + advertising. Revenue is flat after opening. |
| Gross revenue difference due to 21-month delay | $986,832 foregone relative to earlier opening | $986,832 additional gross revenue | Shown for explanation only. Already included in the gross revenue row; not added again as a cost or benefit. |
| Revenue less installed capital and electricity Same 5-year project window | $126,625.55 | $1,110,016.77 | $983,391.21 estimated economic advantagefor battery-integrated charging, including the earlier revenue start. |
These are cash-flow estimates before unpriced costs, not net profit. Maintenance, software, insurance, payment fees, financing, taxes and battery replacement are excluded. Construction and all revenue assumptions are illustrative, scaled from the Word document. Electricity uses the workbook’s stored estimated SDG&E EV-HP rate basis identified as August 1, 2026; it is not a current utility quotation. Monthly bills use annual averages; seasonal start dates and battery dispatch have not been simulated.
Five full operating years for battery-integrated charging — reference only
If you want to show 60 operating months for battery-integrated charging, its three-month construction period makes that 63 months from project start. For three chargers, 60 operating months would generate $2,592,000 charging revenue + $155,520 LCFS + $72,000 advertising = $2,819,520 gross revenue. This reference is not used in the 60-month comparison above. At that same 63-month project endpoint, traditional charging would operate for 39 months, not 36.
Compare the complete cost of traditional and battery-integrated 200 kW DC fast charging.
The charger purchase price is only one part of the decision. A useful comparison connects equipment, electrical construction, utility rates, operating needs, and the value of getting a site into service.
Compare upfront investment and ongoing electricity costs
These planning examples use the supplied True Total Cost of Ownership document and its workbook-derived electricity estimates. Equipment and construction figures are illustrative allowances, not vendor or contractor quotations.
Traditional 200 kW DC fast charger
$220,000
Illustrative installed cost per charger.
Battery-integrated 200 kW charger
$215,250
Illustrative installed cost per charger.
Illustrative equipment and installation costs — per charger
| Cost component | Traditional 200 kW | Battery-integrated 200 kW |
|---|---|---|
| Charger purchase price | $60,000 | $200,000 |
| Breaker allowance | $4,000 (500 A) | $250 (100 A) |
| New distribution panel / switchgear | $6,000, if required | $0 assumed |
| Transformer upgrade | $75,000 | $0 assumed |
| Installation | $75,000 | $15,000 |
| Total illustrative installed cost | $220,000 | $215,250 |
| Upfront difference | $4,750 lower per battery-integrated charger (2.2%). | |
Service voltage, breaker sizing, available power, construction scope, and local requirements must be confirmed for each installation. The $6,000 distribution allowance applies only where needed. If that traditional allowance is unnecessary, the traditional total falls to $214,000—$1,250 below the battery-integrated example. Do not multiply shared transformer or switchgear costs by the charger count without a site-specific design.
SDG&E estimated electricity costs — three chargers at one meter
Both alternatives use the workbook’s EV-HP scenario. Figures are based on stored estimated SDG&E rates identified as effective August 1, 2026, for secondary, bundled, non-CPP service. They are not a current utility quotation. Tariff eligibility, subscription-block treatment, and actual meter demand need confirmation.
| Site-level metric | Traditional | Battery-integrated |
|---|---|---|
| Number of chargers | 3 | 3 |
| Maximum modeled meter demand | 600 kW | 180 kW |
| Summer monthly electricity bill | $27,094.90 | $16,771.49 |
| Winter monthly electricity bill | $21,860.10 | $14,911.05 |
| Annual electricity bill | $288,495.20 | $188,234.80 |
| Annual electricity difference | $100,260.40 lower in the modeled battery-integrated case (34.8%). | |
| All-in electricity cost per purchased grid kWh | $0.3005 | $0.1961 |
Both cases deliver 72,000 DC kWh per month and purchase 80,000 grid kWh at the assumed 90% efficiency. The model uses three chargers, four full-output-equivalent hours per charger daily, and 30 days monthly. It assumes different time-of-use energy allocations: 40% peak / 35% off-peak / 25% super off-peak for traditional charging, and 10% / 25% / 65% for battery-integrated charging. Battery capacity and hourly recharge feasibility remain to be validated.
Electricity estimates include modeled energy, basic service, subscription, and applicable demand charges. They exclude equipment, installation, O&M, financing, battery replacement, taxes, and incentives. The per-charger installed-cost table and the three-charger electricity example are separate scenarios; they have not been combined into a validated full-lifecycle TCO.
The cost of waiting — a separate single-charger example
The document compares an assumed 24-month traditional deployment with a 3-month battery-integrated deployment. Within the same first 24 months, the earlier installation has 21 operating months.
| Assumption or result | Traditional | Battery-integrated |
|---|---|---|
| Assumed time to operation | 24 months | 3 months |
| Operating months within the first 24 months | 0 | 21 |
| Monthly charging revenue once operating | $14,400 | $14,400 |
| Monthly advertising / eligible LCFS revenue | $400 / $864 | $400 / $864 |
| Gross revenue within the first 24 months | $0 | $328,944 |
$328,944 is an illustrative gross revenue opportunity, not profit or guaranteed savings. It equals 21 × ($14,400 + $400 + $864), before electricity and other expenses. Charging revenue assumes one charger delivering 200 kW for four equivalent hours per day, 30 days per month, at $0.60/kWh. Advertising contracts, LCFS eligibility and credit rights, utilization, and deployment dates must be established. This single-charger example is not added to the three-charger electricity results.
Source: True_Cost_of_Ownership_SDG&E_Updated_Validated(3).docx, sections 1, 2A and 5. The detailed workbook scenario and limitations follow below. Product names have been generalized to describe the two charging technologies.
Traditional 200 kW charging
The utility supplies the power needed during each charging session. The project must align charging demand with available site capacity and the cost of any required upgrades.
Battery-integrated 200 kW charging
An integrated battery stores energy and supplements the utility connection during vehicle charging. This can reduce peak grid demand, while introducing battery capacity, recharge, and lifecycle considerations.
Compare the full project
Use the same delivered energy, fleet workload, charger count, and analysis period for both options. On phones, each comparison appears as a labeled card.
| Cost or operating factor | Traditional 200 kW | Battery-integrated 200 kW |
|---|---|---|
| Charging output | Up to 200 kW, subject to the vehicle and operating conditions. | Up to 200 kW, subject to the vehicle, battery state of charge, temperature, and equipment limits. |
| Utility connection | Grid supply must support the charger input and other site loads; input can exceed DC output because of losses. | The battery supplements grid input during charging. Required grid power depends on the selected system and operating schedule. |
| Electrical construction | Evaluate service capacity, transformer, switchgear, panel, breaker, conduit, trenching, and utility work. | Evaluate the same items against the lower input requirement. Some upgrades may be reduced or avoided; verify with the utility and electrical designer. |
| Equipment investment | Compare quoted charger, installation, commissioning, warranty, and software costs. | Include integrated battery and controls, commissioning, warranty, and any battery service or replacement allowance. |
| Utility operating costs | Model energy, demand, subscription tiers, fixed charges, and time-of-use periods at the meter. | Model those same tariff components using the grid-input profile, recharge schedule, standby use, and storage losses. |
| Charging throughput | Evaluate actual simultaneous vehicle demand, power sharing, and available service. | Check battery capacity, usable energy, reserve, recharge time, and back-to-back sessions. A 200 kW rating does not mean continuous 200 kW delivery. |
| Deployment and opportunity cost | Include utility and construction lead times, temporary charging, financing carry, and delayed net operating income. | Compare the actual deployment schedule. Earlier operation may have value where existing service is sufficient; savings are site-specific. |
| Lifecycle and operations | Include maintenance, networking, payment processing, insurance, downtime, and end-of-life value. | Include the same costs plus battery degradation, service, and replacement where applicable. |
One charger versus three: compare costs at the meter
Subscription levels and demand charges depend on the serving utility’s tariff, metered load, and account configuration. Charger count alone does not determine the bill.
Illustrative power comparison — not a utility quote
If each traditional charger delivers 200 kW simultaneously, one charger represents 200 kW of DC output and three represent 600 kW. AC input will be higher after losses. If a selected battery-integrated system is configured to draw a maximum of 60 kW per unit, one unit has a 60 kW grid-input limit and three units total 180 kW before other site loads or shared controls.
The 60 kW figure is an example, not a specification for every battery-integrated charger. Lower grid input does not reduce the energy vehicles need. Check recharge time, storage losses, and battery depletion against the proposed daily schedule.
For a subscription tariff, identify the applicable meter-level capacity band and any overage provisions. For a demand tariff, model the billing interval, ratchets, time-of-use demand, and coincident building loads. Model each meter separately.
Inputs for your ownership comparison
| Input group | Information to collect for each option |
|---|---|
| Site and utilization | Charger count, ports per charger, vehicles per day, delivered kWh per day, session timing, operating days, and existing site load. |
| Equipment and construction | Equipment quote, engineering, installation, utility application fees, transformer, switchgear, distribution panel, breaker, conduit, trenching, permits, and commissioning. Separate utility-paid and owner-paid work. |
| Utility rates | Utility and tariff, time-of-use energy prices, monthly demand charges, subscription bands, overages, fixed fees, grid-input limit, and charging/recharge schedule. |
| Battery operation | Usable battery kWh, reserve, conversion efficiency, recharge limits, expected degradation, warranty, and replacement allowance. |
| Operating costs | Maintenance, software, network fees, insurance, payment processing, land or parking costs, and downtime allowance. |
| Schedule and opportunity costs | Months to operation, temporary charging, financing carry, and delayed net contribution from charging, advertising, or environmental credits. Avoid counting gross revenue as profit. |
| Funding and finance | Confirmed incentives, customer contributions, financing terms, analysis period, discount rate, escalation assumptions, and residual value. Evaluate tax effects separately with your adviser. |
How the ownership calculation will work
Total ownership cost combines upfront investment, utility bills, operating and replacement costs, financing, and deployment impacts, less confirmed incentives and residual value. Compare both total cost and cost per delivered kWh over the same period.
Keep charging revenue and other project income in a separate cash-flow view. This makes equipment ownership costs and project returns easier to assess without double-counting.
Building the site-specific model
The estimates above show the document’s illustrative installed costs and the workbook’s electricity scenarios. The next step is to replace zero placeholders with equipment and construction quotes, validate the tariff and charging schedule, and add editable inputs. The figures do not update automatically when the workbook changes.
What will charging cost at your site?
Bring your electricity bill, site location, fleet or utilization plan, and equipment quotes. Open Energy Alliance can help compare the complete project economics.
Discuss Your ProjectPlanning resources
DOE: Charging infrastructure procurement and installation
DOE: Charging infrastructure operation and maintenance
Total estimated economic advantage
3 chargers · 60 months from project start
$983,391.21
Revenue less installed capital and electricity:
Traditional: $126,625.55 · Battery-integrated: $1,110,016.77
Includes 36 operating months for traditional and 57 for battery-integrated charging, after 24-month and 3-month builds. Charging revenue at $0.60/kWh, LCFS and advertising follow the document’s assumptions scaled to three chargers. Uses estimated SDG&E EV-HP costs. Excludes unpriced operating, financing, tax and battery lifecycle costs. Not guaranteed savings or net profit.